Wednesday, August 18, 2010

Forming


Concrete apron left.  Lower interior level middle.  Cistern mezzanine right.  [Note 'brick nogging' exposed by removal of siding  in upper left corner of house wall.]


Cistern mezzanine

Piping leads to screening barrel, which distributes to pair
of 6500 liter tanks in near left corner of mezzanine.  Foundation is insulated grade-beam.  Two-inch foam is twelve inches vertical with two feet horizontal extending away from the structure, which is an approved method in the NY building code.

Downspout piping detail with tie-in for new roof of this structure.
Screening barrel detail.
[Small pipes are just-in-case conduits.]


20 September 2009, yet another in a series of fabulous
late-summer days that year.